top of page

Abacot Hill Development News

July 2, 2026

  • Servicing of the underground pipes are completed as well as the paving of the site

  • Next is the power and gas which will be less noisy/intrusive and take a few weeks

  • The builder is still working away at completing the model homes so that activity is still ongoing and is expected to be complete by the end of August

Note: The two large trees at the entrance to Abacot Hill were cut down on Tuesday, June 29. This came as a surprise to any residents passing by and was not in the original development plans. According to the builder, this decision was out of their hands. “In regards to the trees, the City will eventually be taking them down fully. They were unfortunately in the way of the final curb locations. I was pushing hard on the City to allow us to modify these to keep the trees but truck turning capabilities (of fire trucks, garbage trucks, other city vehicles, etc.) took precedence unfortunately.”

April 29, 2026

Work being performed:

  • Site Servicing (installation of underground services and utilities (5-7 weeks)

  • Asphalt Paving and Concrete Works (2-3 weeks)

What to expect:

  • Some of the servicing work is happening directly behind the homes on Sherwood Forrest Circle (1656-1716)

  • Increased onsite activity as work is completed (within allowable working hours as per by-laws)

  • Increased vehicle traffic with material deliveries

  • Temporary closures/ lane restrictions at Deers Wold/Sherwood Forrest for entrance modifications

  • Temporary lane closures on Dundas for servicing connections

October 7, 2025

The project is currently in the earthworks stage of redevelopment. This phase involves the installation of erosion and sediment control measures, stripping and removing topsoil, excavating and grading the site in preparation for servicing, and hauling excess material off-site. 

 

Residents are advised that during this period, there may be increased noise, dust and traffic. The primary access for construction vehicles will be the entrance on Sherwood Forrest Circle, with the Dundas entrance being used infrequently as needed. The hauling of material off-site will primarily follow the routes along Deers Wold and King Forrest Drive.

 

Weather permitting, it is anticipated that this stage of work will take approximately six to seven weeks to complete. Argo appreciates your understanding and patience during this time. 

Also, after listening to feedback from interested buyers and neighbours, Hallett Homes has updated the site plan. The development will now include 41 homes instead of 56. The number of 57-foot lots will remain the same, there will be fewer 33-foot lots, and the introduction of new 49.5-foot lots. Hallett Homes also plans to build 3–4 model homes, which will allow people to explore different layouts, etc. As with any project, details may evolve as it moves forward.

© Copyright 2025. All rights reserved. Website designed by Pinch & Dash

bottom of page